ESPNWNBA Finals Game 3 live updates, analysis and highlightsESPN DeportesAmérica aplasta al Atlas y firma una noche redonda en GuadalajaraThe Jerusalem PostUS, Israel have detailed plans for renewed Iran strikes focusing on short, intense attacks - reportPunchOndo crash: Residents lament non-fumigation of site한겨레한은, “올해 성장률 3.3% 상당 폭 상회할 것”Daily MaverickAMABHUNGANE ANALYSIS: Gloves come off between PetroSA and ex-partner, Nako EnergyZDF heuteEntdecken Sie das ZDF-NachrichtenstudioUOLFlávio Bolsonaro fez festa em lancha com lobistas e prostitutas durante a pandemia, diz revistaGIGAZINE文化についてAIに質問すると日本が選ばれやすい傾向がある、8モデル・24言語で回答の偏りを調査New Straits TimesTuJu temporarily offline amid system upgradesLa NaciónLa carta que Robert De Niro le escribió a la viuda de Luis Brandoni a seis meses de su muerte: “Perdona que me haya tomado tanto tiempo”DeadlineSara Bareilles Is “Still Holding Out” For A ‘Girls5eva’ Movie: “We’d Do It In A Heartbeat”
The Daily Newsstand · Free, Always
Thursday, October 22, 2026

NGCP: Visayas grid on red, yellow alerts on Thursday, Oct. 22, 2026

Translate

Make this your preferred source to get more updates from this publisher on Google.

The Visayas grid will be placed on red and yellow alert status on Thursday, October 22, 2026, due to the unavailability of power plants in the region and limited power imports from Mindanao.

In an advisory, the National Grid Corporation of the Philippines (NGCP) said red alert will be raised from 5 p.m. to 6 p.m., while yellow alert will be from 6 p.m. to 7 p.m.

A red alert status is issued when power supply is insufficient to meet consumer demand and the transmission grid’s regulating requirement.

On the other hand, a yellow alert is issued when the operating margin is insufficient to meet the transmission grid's contingency requirement.

The Visayas grid has an available capacity of 2,608 MW against a peak demand of 2,581 MW, as 599.1 MW remain unavailable to the grid.

The following were cited as factors that contributed to the red and yellow alerts in the Visayas grid:

  • Unavailability of Visayas’ large coal plants PEDC 3 and KSPC 1.
  • Limited power imports from Mindanao due to the planned outages of GNPK 4, TSI 2, and the unplanned outage of Pulangi 4 U2

The grid operator said five plants are on forced outage in October, two plants since September, three plants since August, one plant since June, three plants since May, three plants since 2025, one plant since 2024, two plants since 2023, and one plant since 2021, while 21 plants are running at derated capacity. —AOL, GMA News

View the original on GMA News →