ESPNHow a mass Man City player exodus would warp the transfer marketPunchNGF mourns victims of Ondo aircraft crashDaily MaverickSHARE WITH US: Online schools in South Africa: what should parents know?The Jerusalem PostFormer German spy chief detained on suspicion of espionage and treason, Bild reportsZDF heuteAktuelle Pressemitteilungen des ZDFSouth China Morning PostGreenpeace catches Hong Kong geopark ‘golden week’ visitors damaging marine lifeCapital FMGovt fast-tracks passport decentralisation as Malindi, Nyeri offices near completionNHK 社会JR東日本 大雨災害を受け運転規制のあり方を検証へNPRVietnamese police arrest 12 suspected of prowling city streets at night, snatching cats for meatکیهان لندنرئیس پیشین سرویس اطلاعات خارجی آلمان به اتهام جاسوسی بازداشت شدABC NewsTrump says his super PAC will now pay for controversial taxpayer-funded promo adsAntara NewsIndonesia targets Rp3,839 tln in downstreaming investment through 2029
The Daily Newsstand · Free, Always
Tuesday, October 6, 2026

Parliament’s crane operators face unique challenges at lofty heights

Translate
Parliament Hill
Construction crane is seen working around the Peace Tower on Parliament Hill in Ottawa on Thursday, Jan. 22, 2026. Photo by HYUNGCHEOL PARK /Postmedia

OTTAWA — Andrée-Anne Pare is one of the handful of Canadian female construction crane operators on Parliament Hill during the second phase of the estimated $4.5 billion to $5 billion renovation of the buildings.

Sign In or Create an Account

or

In this video she tells us of the unique challenges of operating one of the five cranes labouring over Parliament Hill.

The first phase of this massive Parliamentary project, the deconstruction, which included both demolition and excavation, is now complete. The second phase, the rebuilding, is currently in progress. This phase is the creation of the new parliamentary welcome centre and upgrades to the historic Centre Block, including restoring all of the heritage elements while modernizing the old structure and its facilities. The third phase, the “fit-out,” has not yet begun, and involves putting in the final finishes and restored heritage elements.

Main construction will be complete between 2030 and 2031. The Centre Block will reopen about one year later.

The video includes some stunning high aerial footage provided to Postmedia by Public Services and Procurement Canada, who for safety reasons don’t allow media to film on their active construction site.

As of March of this year, up to 800 workers are on site daily (this number will peak at over 1,500). Approximately 95 per cent of the companies that have worked on the project are Canadian owned, with involvement from over 400 companies across eight provinces, including some direct Indigenous participation.

Crane operators bring home some of the biggest paycheques on big construction sites but that’s partly because they work 10 to 11 hour shifts. Becoming a crane operator requires both in-class study and an apprenticeship. Most programs require a high school diploma (Grade 12), a clean driver’s record, and often a specific commercial driver’s license (like a Class 3 or Class 1 with air brake endorsement) especially for mobile cranes.

Our website is the place for the latest breaking news, exclusive scoops, longreads and provocative commentary. Please bookmark nationalpost.com and sign up for our daily newsletter, Posted, here.

Join the Conversation

This website uses cookies to personalize your content (including ads), and allows us to analyze our traffic. Read more about cookies here. By continuing to use our site, you agree to our Terms of Use and Privacy Policy.

View the original on National Post →

KioskNews shows a cleaned-up reading view extracted from the publisher’s page — the original always lives on their site, not ours.