The Jerusalem PostRussians vote in election that Putin sees as barometer of public support for his war in UkraineESPN DeportesRed Sox sorprende a Rangers con jonrón en la octava y evita la barridaESPNDC Belichick resigns as UNC investigation finds disregard for conductDaily MaverickConsistency proved key in Sinesipho Dambile’s remarkable yearInquirerGatchalian flags P295-M fees paid due to transport project delaysRTP DesportoAdeptos do Torreense falam em vitória históricaוואלהבית המשפט קיבל את עתירת אגם צרפי ומתח ביקורת על שב"סAntara NewsTomorrow, Jakarta to turn off lights for 60 minutes for Ozone DayVanguardLagos youths trained to spot fake news, manipulated contentTVN24W weekend pożegnamy lato. W tej prognozie widać śniegХабрЭволюция пайплайна метрик: как менялась архитектура с ростом нагрузкиn-tvDeutsche Fahne "zurückholen"?: Warum der Kanzler sich besser nichts von Jürgen Klopp abguckt
The Daily Newsstand · Free, Always
Friday, September 18, 2026

Nearly 300 higher education sites now connected under nationwide Wi-Fi project

Translate
Communications Deputy Minister Teo Nie Ching (left) checks the internet speed during the completion ceremony for the Universal Service Provision Wi-Fi Project for Public Higher Education Institutions at Universiti Teknikal Malaysia Melaka in Durian Tunggal, Alor Gajah, on September 18, 2026. Also present was Malaysian Communications and Multimedia Commission Southern Regional Office Senior Director Ts. Rizal Abd Malek (second, left). — Bernama pic

Communications Deputy Minister Teo Nie Ching (left) checks the internet speed during the completion ceremony for the Universal Service Provision Wi-Fi Project for Public Higher Education Institutions at Universiti Teknikal Malaysia Melaka in Durian Tunggal, Alor Gajah, on September 18, 2026. Also present was Malaysian Communications and Multimedia Commission Southern Regional Office Senior Director Ts. Rizal Abd Malek (second, left). — Bernama pic

First Published: Friday, 18 Sep 2026 7:20 PM MYT

MELAKA, Sept 19 — The Public Higher Education Institution (IPTA) Wi-Fi project, covering 539 locations nationwide, is expected to be fully completed by September, with 55 per cent, or 294 locations, already having access to Wi-Fi, Deputy Communications Minister Teo Nie Ching said.

She said the RM664 million project, fully funded by the Malaysian Communications and Multimedia Commission (MCMC) through the Universal Service Provision initiative, would help upgrade infrastructure and improve internet coverage across campuses.

“We have embarked on a project to install tens of thousands of access points equipped with high-end Wi-Fi technology, specifically Wi-Fi 6 or Wi-Fi 7.

“This project focuses on strategic locations across campuses, including lecture halls, laboratories, libraries, student centres, residential colleges and hostels,” she told reporters after visiting the IPTA Wi-Fi Project Phase 3 site at Universiti Teknikal Malaysia Melaka (UTeM) here today.

She said the project covers 539 locations, involving IPTA and skills training institutions under Majlis Amanah Rakyat (Mara) and the Ministry of Human Resources (Kesuma).

Teo said Phases 1 and 2 of the project had been completed at 191 locations, with Phase 3 implementation now underway at institutions under Mara and Kesuma.

“For Phase 3 of the project, work has been completed at 42 of the 204 locations, or 21 per cent, while the remaining locations are still undergoing network provisioning and installation.

“As for institutions under Mara, work has been completed at 60 of the 110 identified locations, or 55 per cent, while for those under Kesuma, work has been completed at one of the 34 identified locations,” she said.

Commenting on the project’s implementation in Melaka, Teo said the IPTA Wi-Fi project in the state had reached 44 per cent completion, with 1,399 new access points activated at 10 IPTA as of last August.

She said UTeM had made good progress under Phase 3, with 302 additional access points installed on Aug 27, ahead of the MCMC’s original target date of Sept 23.

“Under Phase 3, 302 additional APs were installed here at UTeM, with the work completed on Aug 27, ahead of the MCMC’s original target date of Sept 23.

“In total, UTeM now has 410 operational APs, including the 108 APs installed under Phase 2 in June 2025,” she said.

Meanwhile, UTeM student representative Muhammad Quwayyis Khairuddin, 21, said the installation of additional high-speed Wi-Fi APs was crucial, particularly for students living in residential colleges and those using other strategic locations across the university campus.

“This is a meaningful contribution from the Ministry of Communications, as every student here needs reliable internet access to complete projects and assignments.

“Although the internet service was already good, the addition of these APs has further improved internet connectivity across the campus,” he said. — Bernama

* Editor’s note: IPTA stands for Institusi Pengajian Tinggi Awam, the Malay name for Public Higher Education Institutions. 