ESPNFollow live: Rays extend lead after another defensive miscue by YankeesESPN DeportesEN VIVO: Rays recupera ventaja con ataque en la quintaThe Jerusalem PostBoard of Peace ‘not stepping back’ from Gaza plan ahead of Israeli elections - reportInquirerDefense team did not intend to threaten anyone – PoaPunchNigeria overtakes four nations in Africa investment ranking한겨레‘알래스카 LNG 추진계획’ 빠진 산업부 업무보고…국감서 “국익 최우선” 강조VarietySkydance to Fully Reorganize International; Kevin MacLellan Will Not Lead Key GroupZDF heuteAktuelle Pressemitteilungen des ZDFUOLApucarana aprova idade mínima de 16 anos para scooter, bikes e patinetes elétricosNew Straits TimesBahrain part ways with Talajic after Gulf Cup early exit3DNewsБывшие инженеры Groq подали в суд на правление из-за неправомерной сделки с Nvidia경향신문유류세 인하 5년…온실가스 400만t 감축 기회 놓쳤다
The Daily Newsstand · Free, Always
Tuesday, October 6, 2026

LCS 1, LCS 2 piping, wiring work remain behind target, A-G’s report finds

Translate
According to the Auditor-General’s Report (LKAN) 2/2026, as of June 25, piping work on LCS 1 and LCS 2 had reached only 87.70 per cent and 74.73 per cent, respectively, resulting in delays of 12.30 and 25.27 percentage points. — Bernama pic

According to the Auditor-General’s Report (LKAN) 2/2026, as of June 25, piping work on LCS 1 and LCS 2 had reached only 87.70 per cent and 74.73 per cent, respectively, resulting in delays of 12.30 and 25.27 percentage points. — Bernama pic

First Published: Tuesday, 06 Oct 2026 9:05 AM MYT

KUALA LUMPUR, Oct 6 — Progress on piping and wiring work for Littoral Combat Ships (LCS) 1 and 2 remains behind target, putting subsequent construction activities and the targeted physical handover (PHO) of LCS 1 at risk.

According to the Auditor-General’s Report (LKAN) 2/2026, as of June 25, piping work on LCS 1 and LCS 2 had reached only 87.70 per cent and 74.73 per cent, respectively, resulting in delays of 12.30 and 25.27 percentage points.

The delays involved 4,113 pipe spools following design changes that required rework, including pipe rerouting to meet performance targets and resolve clashes.

Meanwhile, wiring work on LCS 1 and LCS 2 had reached 51.41 per cent and 43.49 per cent, respectively, representing delays of 48.59 and 56.51 percentage points.

According to the report, the delays in wiring work are partly due to rework following design revisions involving 95 cable tray changes and 85 penetration changes.

It also said delays in piping and wiring work, which are part of the shipbuilding activities, could affect subsequent construction work and the targeted physical handover (PHO) of LCS 1.

Based on feedback from the Defence Ministry (Mindef) on July 20 and August 13, piping work for LCS 1 and LCS 2 uses a combination of pipe spools from the original and revised designs, while LCS 3 to LCS 5 use the revised design exclusively.

The delay was first identified in November 2025 following a comment from the Design Authority, Naval Group. As of July 2026, piping work on LCS 1 had reached 100 per cent, while LCS 2 stood at 96 per cent.

Mindef said the improved progress was driven by the contractor’s decision to introduce three work shifts from January 23, 2024, to accelerate completion.

However, the LCS Project Management (PPLCS) could not verify the progress of the piping and cabling work because, as of July 2026, the contractor had not submitted reports or evidence that the work had been carried out in line with the reported progress.

PPLCS will only verify work progress formally submitted by the contractor, with only work that has been physically verified and fully supported by documentation recognised as confirmed progress.

PPLCS was also informed that the actual physical progress of some activities exceeded the verified progress, but stressed that only verified and confirmed work is recorded, with unverified work excluded. — Bernama 