ESPNThe only MLB playoff preview you need: World Series odds, likely MVPs and how far all 8 remaining teams will goESPN DeportesBraves derrota a Phillies a punta de jonrones y conquista el boleto a Serie DivisionalThe Jerusalem PostJewish groups hail California law making it the first state to list ‘Jewish’ as an ethnicityPunchObi: I’ll spend holidays in Zamfara, Borno if electedInquirerEx-BFP chief pleads not guilty to graft over alleged P4M bribeالنهارمن النيل إلى التمرّد... لماذا تُقحم إثيوبيا مصر في أزمتها؟The Sydney Morning HeraldGreene compo revealed as Cats snare Giants’ greatest player; door ajar for De Goey to leave PiesSoompiBreaking: T.O.P And Nana Confirm They’re DatingNew Straits TimesLee Chean Chung resigns as Petaling Jaya MP경향신문입주민-관리종사자 서로 배려하는 아파트···경기도, 착한아파트 6개 단지 선정Daily MailGypsy-Rose Blanchard's ex-fiancé Ken Urker dead at 33 as his body is discovered at Louisiana home on his birthdayLa NaciónRecta final: por qué hay que mirar las elecciones en Brasil y cómo pueden impactar en la región
The Daily Newsstand · Free, Always
Friday, October 2, 2026

High-speed rail costs could reach $113 billion, 25% more than estimated, PBO warns

Translate
Alto
Kingston-area opponents of the Alto high-speed rail project lead a march with protestors from Quebec toward a rally on Parliament Hill on Wednesday June 10, 2026 in Ottawa, Ont. Photo by Elliot Ferguson /The Kingston Whig-Standard

OTTAWA — A new report by Ottawa’s fiscal watchdog warns that the planned high-speed rail project from Toronto to Quebec City could cost as much as 25 per cent more than the Carney government’s highest estimates.

Sign In or Create an Account

or

The Parliamentary Budget Officer (PBO) estimated in a report released Thursday that the project’s costs would run between $75-billion and $113-billion, compared to the government’s estimated range of $60 billion to $90 billion. The upper end of the PBO’s estimated range is 25.6 per cent higher than the government’s.

“This range reflects the considerable uncertainty inherent in large-scale rail infrastructure projects,” the report said.

The report raises fresh questions about one of the Liberal government’s signature projects, as Prime Minister Mark Carney tries to balance his desire to bolster Canada’s infrastructure and the country’s growing debt.

The high-speed rail project would add about 1,000 kilometres of electrified high-speed rail using trains designed to travel up to 300 kilometres per hour. The project was unveiled by former prime minister Justin Trudeau in February 2025, just weeks before he left office. It was referred to Carney’s new Major Projects Office in September 2025. Construction is expected to begin in 2029 and the vast majority of the bill will be paid by the federal government, although there may be private sector involvement.

But the project’s rising cost estimates may not be finished. PBO Annette Ryan also warned that any major changes to the rail plan, such as diverting the line to run through Kingston, Ont. or adding tunnels or overpasses would add significantly to the project’s cost.

The PBO’s analysis concluded that about 15 kilometres of tunnel would be needed to connect Laval, Que. and Montreal. And the government announced in June that Kingston is being considered for a potential stop.

The PBO report, based largely on previous high-speed rail projects in Europe and the United States, notes that the details of the proposed route have not yet been made public, and that much of the route will need to go through costly, rocky Canadian Shield. Dense, urban areas, such as the Montreal area, are also more difficult and costly for a rail project.

The report also tamps down the economic benefits of constructing the high-speed rail project, saying Canadians should expect only a “modest” near-term economic stimulus. For this part of the analysis, the report focuses on the Ottawa-Montreal leg of the proposed project because it’s expected to be completed first. Each dollar spent on construction would boost gross domestic product, or the size of the economy, by about 80 cents during the first year of construction, growing to about 90 cents by the fifth year.

Construction would mean about 4,300 new jobs during the first year, the report said, rising to about 9,000 by the fifth.

The Canadian Taxpayers Federation said the PBO report adds another reason to scrap the entire high-speed rail project. “The government doesn’t have enough spare cash to buy a model train, let alone a train that could cost more than $100-billion,” Franco Terrazzano, the organization’s federal director said in a release.

Dan Albas, the Conservatives’ transport critic, said his party will cancel the project because of its cost, which he pointed out is greater than the federal government’s current deficit. “Canadians are out of money,” Albas said in a release.

In a prepared statement, the office of Transport Minister Steven MacKinnon said the government will review the PBO report and called the project “generational.” MacKinnon’s statement did not address the PBO’s analysis about the cost of the project.

The report also said that recent federal legislation designed to encourage large projects, particularly the Building Canada Act, and the High-Speed Rail Network Act, could help streamline approvals and land acquisition. That could allow the high-speed rail project to advance more quickly and avoid the cost overruns that have plagued some projects in other jurisdictions.

The analysis does not factor in the costs of financing the project through higher taxes, reduced spending on other things and higher deficits, nor does it try to account for any possible productivity gains from the new line or the added costs of potentially displacing the advance of other construction projects.

The project was mandated to Crown corporation Alto in partnership with Cadence, a consortium chosen to design, build and operate the rail line. Alto has completed its first major round of consultations with Indigenous communities and the broader public.

National Post

Our website is the place for the latest breaking news, exclusive scoops, longreads and provocative commentary. Please bookmark nationalpost.com and sign up for our politics newsletter, First Reading, here.

Join the Conversation

This website uses cookies to personalize your content (including ads), and allows us to analyze our traffic. Read more about cookies here. By continuing to use our site, you agree to our Terms of Use and Privacy Policy.

View the original on National Post →

KioskNews shows a cleaned-up reading view extracted from the publisher’s page — the original always lives on their site, not ours.